Laying the felt as you work the paper can be tacked down in the center so it won t blow away.
Overlap roof felt paper.
Adjust the bottom of the felt if necessary to keep it flush with the gutter apron.
Adjacent pieces of drip edge should overlap at least 2 inches 51 mm.
Remember to always overlap roof paper at valley ridges and hips by six inches.
Nail down the last few feet of the first course of felt.
Overlap the end of a roll about 4 inches with the start of a new roll and fasten both pieces to the.
Video of the day.
The drip edge should extend at least 2 inches on the roof.
Position the next course of felt so that there is a 2 overlap of the first course of felt.
Roofing felt is required to overlap 2 inches over the lower felt course.
Trim any felt that overlaps the rake.
Also called roof felt or builder s felt overlapped tar paper creates a water barrier that is your home s last line of defense against the elements if your shingles are damaged by wind hail or.
The vertical leg of the drip edge should be at least 1 5 inches wide and extend at least 0 25 inches below the sheathing.
It s best to wear gloves and protective eyewear for safety purposes.
When you arrive at the rake the paper should be cut flush with a knife and then adjusted to line up with the chalk line.
Cut a slit from the side of a paper roll to accommodate vent pipes.
Step 4 continue rolling out the felt until you reach the roof hip on the other end.
Where a roll ends and a new one is begun the two rolls should be overlapped by.
Insert staples with a hammer stapler 12 inches apart along the top and bottom edges of the felt paper as you roll it out along the roof.
Pay special attention to movements on top of any roof.
The overlapping felt creates a secondary barrier for moisture and wicks water away from the shingles above and the sheathing below.